Homagama Court Complex

Open (04.01.2017)

TEC RS.Mn Cumulative Exp. 31.08.2017 Physical Progress
470.81 491.59 100%

    

Wattala Court Complex Stage I

TEC RS.Mn Cumulative Exp. 31.08.2017 Physical Progress
194.11 148.41 99%

  

Wattala Court Complex Stage II

TEC RS.Mn Cumulative Exp. 31.08.2017 Physical Progress
170.54 43.18 20%

Galagedara Court Building

Open (22.05.2017)

TEC RS.Mn Cumulative Exp. 31.08.2017 Physical Progress
70.11 65.24 100%

  

Matara Court Complex Stage II

TEC RS.Mn Cumulative Exp. 31.08.2017 Physical Progress
1119.55 402.64 28%

Galle Court Complex

TEC RS.Mn Cumulative Exp. 31.05.2017 Physical Progress
823.15 372.34 47%

  

New Project 2017

Project TEC RS.Mn Allocation -2017 (Rs.Mn)
Gampola District Magistrate Court 458 150
Ruwanwella District Magistrate Court 275 120
Passara Magistrate Court 114 50
Mullaitive District Court 414.34 100
Mankulam Circuit Magistrate Court 463 50
Laggala New Court Complex Stage I 88.7 53.36
Jaffna High Court Building 242 100
Polonnaruwa Court Complex 382 150
Anuradhapura Court Complex 370 150
Matale High Court 400 100

Events